Home News TCN Faults IKEDC Over Misleading Attribution of Power Outages to Grid Instability

TCN Faults IKEDC Over Misleading Attribution of Power Outages to Grid Instability

0

The Transmission Company of Nigeria (TCN) has faulted Ikeja Electric (IKEDC) over its attribution of several Band A feeder outages recorded on November 3 and 4, 2026, to “grid instability,” insisting that the claim is inaccurate and misleading.

TCN, in a statement signed by its management on November 6, said the determination of the root causes of disturbances, shortfalls and interruptions on the national grid falls exclusively within the functions of the Nigerian Independent System Operator (NISO), as provided under Section 67 of the Electricity Act 2023.

The company stated that IKEDC, like other electricity market participants, lacked the authority to independently determine the causes of grid disturbances, adding that NISO had not attributed the outages mentioned in IKEDC’s notice to TCN.

According to TCN, NISO’s public clarification issued on November 5 attributed the decline in power generation to gas supply constraints affecting thermal power stations and reduced output from hydroelectric stations due to lower reservoir inflows.

It explained that the reduced generation had affected the energy allocated to distribution companies (DisCos), resulting in fewer hours of electricity supply and increased load shedding across distribution networks.

TCN maintained that the supply shortfall experienced by IKEDC customers was a consequence of reduced generation and energy allocation, rather than any failure of its transmission network.

“TCN can only transmit the energy made available to it and cannot transmit energy that is not generated,” the company stated.

The transmission company further disclosed that records of interruptions across all feeders supplying IKEDC showed that 68 per cent of outages recorded on November 1 and 2 were frequency-control load shedding caused by low generation.

It said 26 per cent of the interruptions resulted from IKEDC’s non-compliance with load allocation by NISO’s National Control Centre or faults and maintenance works on the distribution company’s network.

The remaining six per cent, according to TCN, were linked to its planned maintenance, switching operations or line limitations, stressing that none of the recorded interruptions resulted from TCN equipment faults or trips.

On the 33kV feeders listed in IKEDC’s notice, TCN said 29 of the 46 interruptions were caused by frequency-control load shedding arising from low generation, while 14 were recorded against IKEDC.

It explained that nine of the 14 interruptions resulted from non-compliance with load allocation, while five were caused by faults or trips on IKEDC’s network.
The remaining three interruptions, TCN said, were due to scheduled maintenance on the Ogba–Alimosho line on November 1.
Citing the Rack Centre feeder as an example, the company said the feeder was interrupted on November 2 following a cable fault on IKEDC’s network, which was subsequently repaired by the distribution company’s crew.

TCN also noted that IKEDC’s own notice attributed several feeder interruptions, including those involving MTN, Iju Water Works and Rack Centre, to the distribution company under the “IE” designation for 33kV faults.

The company said IKEDC’s position was inconsistent with the actual state of the Nigerian Electricity Supply Industry, warning that attributing generation-related shortfalls to TCN could misinform customers, undermine public confidence and obscure the real challenges confronting the sector.
TCN therefore urged IKEDC and other distribution companies to desist from making unverified claims about the causes of electricity supply shortfalls, advising them to communicate based on information provided by NISO, the body responsible for grid operations.

It also urged electricity consumers to consult NISO’s official platforms for accurate information on the state of the Nigerian Electricity Supply Industry.

The transmission company, however, sympathised with customers affected by reduced hours of electricity supply, reaffirming its commitment to transmitting all available energy safely, reliably and efficiently within prevailing operational constraints.

It added that it would continue to work with NISO, generation companies and distribution companies to improve electricity supply across the country.