NNPCL has recognized several hurdles that are delaying the commencement of operations at the Port Harcourt refinery. Olufemi Soneye, the Chief Corporate Communications Officer of NNPC, explained that the company has encountered various risks and challenges during the rehabilitation process due to the complexities of this brownfield project.
He noted that essential equipment and processing units’ commissioning began following the mechanical completion of the refinery in Nigeria.
“You may recall that mechanical completion of the PHRC revamp was successfully achieved several months ago, marking a significant milestone in the project. After this, we initiated the commissioning of critical equipment and process units,” Soneye stated.
“However, as is common with brownfield projects of this scale and complexity, we encountered unforeseen risks and challenges. These issues have since been effectively resolved, and commissioning activities have resumed.”
Soneye assured that work is being carried out around the clock to ensure the successful completion of this vital project. When asked about the timeline for completion, he responded, “Shortly.”