Power generation on the national grid has continued to hover above 4,000 megawatts since January this year, following the deployment of transformers, substations and other accessories to boost supply.
Grid performance data obtained from the Federal Ministry of Power in Abuja on Sunday showed that electricity generation on the national grid as at 6am on the same day was 4,456.8MW.
On the preceding day, it was 4,618.8MW (peak generation); and 4,000.2MW (off-peak generation), according to figures obtained by our correspondent the power ministry’s headquarters.
An analysis of randomly picked figures from the grid performance data indicated that power generation had stayed above the 4,000MW mark for months, while the country had yet to record any total grid collapse this year, unlike what happened in 2022.
On March 2 and 3, 2023, for instance, power generation on the grid as at 6am was put at 4,859.8MW and 4,962.7MW respectively, while it was 4,753.9MW on February 23, 2023, as similar generation figures were recorded in the preceding month.
Analysts believe that the current stability of the grid was due to improvements in the deployment of equipment such as transformers, substations and other accessories.
The manager of the national grid – Transmission Company of Nigeria, an agency of the Federal Government, had continued to announce the deployment of transformers and other accessories to power stations across the country.